Part 2Regime for offshore renewable energy permits and infrastructure protection
Provisions relating to both feasibility permits and commercial permits: Permit variations
41Application to amend permit conditions
A permit holder may apply to the Minister to amend the conditions of the permit.
The application must be made at least 90 working days before the relevant date for meeting the condition that is proposed to be amended (but see section 59).
The Minister may grant the application if the Minister—
- has no cause to believe that the permit holder or the development no longer meets the requirements in section 19(1) (in the case of a feasibility permit) or section 29(1) (in the case of a commercial permit); and
- is satisfied that granting the application is appropriate to give effect to the purpose of this Act or to enable the effective administration of the permitting regime.