Part 3Decommissioning of ORE infrastructure
Decommissioning obligation: Who has decommissioning obligation
70Commercial permit holders have decommissioning obligation for ORE generation infrastructure
A person who holds a commercial permit must carry out, and meet the costs of, the decommissioning of all ORE generation infrastructure that is attributable to ORE generation infrastructure activities under the permit (regardless of when the activities to which the infrastructure is attributable took place under the permit).
A person who has ceased to hold a commercial permit, or whose commercial permit has ceased to be current, continues to have a decommissioning obligation in respect of all ORE generation infrastructure that was in place at the time of cessation.
This section is subject to section 72 (which provides for release from a decommissioning obligation in some circumstances).
A person’s decommissioning obligation is not affected by the expiry, revocation, cancellation, or surrender of their permit or marine consent or resource consent (that is, they must still meet the obligation).