Part 4Planning consents
Nature of consents, commencement, duration and review: Duration
165Lapsing of consent
A planning consent lapses on the date specified in the consent or, if no date is specified—
- 10 years after the date of commencement if the consent authorises a renewable energy activity; and
- 5 years after the date of commencement of the consent, in any other case.
However, a consent does not lapse under subsection (1) if, before the consent lapses,—
- the consent is given effect to; or
- an application is made to the consent authority to extend the period after which the consent lapses, and the consent authority decides to grant an extension after taking into account—
- whether substantial progress or effort has been, and continues to be, made towards giving effect to the consent; and
- whether the applicant has obtained approval from persons who may be adversely affected by the granting of an extension; and
- the effect of the extension on the outcomes and policies in a plan; and
- whether substantial progress or effort has been, and continues to be, made towards giving effect to the consent; and
- in the case of a consent authorising a renewable energy activity, the consent authority decides at the consent holder’s request to shorten the period after which the consent lapses under subsection (1)(a).
A person may apply to the Planning Tribunal under clause 15 of Schedule 10 to review a decision to grant an extension under subsection (2)(b).
For the purposes of this section, a subdivision consent is given effect to when a survey plan in respect of the subdivision has been submitted to the territorial authority under clause 17 of Schedule 7, but lapses if the survey plan is not deposited in accordance with clause 23 of that schedule.