Part 4Natural resource permits
Nature of permits, commencement, duration and review: Review of permit conditions by permit authority
188Public notification, submissions, and hearing, etc
Sections 152 and 153 apply, with all necessary modifications, in respect of a review of any natural resource permit as if—
- the notice of review under section 187 were an application for a natural resource permit; and
- the permit holder were the applicant for the natural resource permit.
Sections 144 to 151 apply, with all necessary modifications, as if—
- the review of permit conditions were an application for a natural resource permit for a discretionary activity; and
- the references to a natural resource permit and to the activity were references only to the review of the conditions and to the effects of the change of conditions respectively.
If a plan states that a rule will affect the exercise of existing natural resource permits that are subject to review under section 186(1)(e)(i), a permit authority—
- is not required to comply with sections 144 to 151; but
- must hear submissions only from the permit holder if the permit holder requests (within 20 working days of service of the notice under section 187) to be heard.
When reviewing the conditions of a natural resource permit under section 186(1)(c), the permit authority must serve on the Minister notice of the review, and the Minister may—
- make a submission to the permit authority; and
- request to be heard.