Part 4Natural resource permits
Consideration of application and decision
161Matters relevant to application relating to stormwater network
When considering a natural resource permit application that relates to a stormwater network, as defined in section 5 of the Water Services Act 2021, a permit authority—
- must not grant the permit contrary to—
- a stormwater environmental performance standard; or
- an infrastructure design solution; and
- a stormwater environmental performance standard; or
- must include, as a condition of granting the permit, requirements that are no more or less restrictive than is necessary to give effect to—
- the stormwater environmental performance standard; or
- the infrastructure design solution.
- the stormwater environmental performance standard; or
However, subsection (1)—
- does not apply if an exception under a stormwater environmental performance standard or an infrastructure design solution applies; and
- except as expressly otherwise provided in this Act, does not prevent a permit authority from including, as a condition of granting a natural resource permit, a requirement that relates to any activity, effect, or other matter that a stormwater environmental standard or an infrastructure design solution does not regulate or manage.