Part 1BPermits, access to land, and other matters
Decommissioning of petroleum infrastructure and wells: Decommissioning obligations in relation to wells
89SObligations of licence holders: decommissioning of wells
A person who holds or will hold a licence at the time the obligation to plug and abandon 1 or more wells is required to be completed must carry out, and meet the costs of, plugging and abandoning all wells—
- drilled or used for the purposes of, or otherwise related to, activities authorised by the current licence, and all relevant older wells; and
- in a case where only part of the licence area is to be surrendered, located in the area of the licence that is to be surrendered, and all relevant older wells.
-
Repealed -
Repealed -
Repealed -
Repealed
Notes
- Section 89S: inserted, on , by section 18 of the Crown Minerals (Decommissioning and Other Matters) Amendment Act 2021 (2021 No 53).
- Section 89S heading: amended, on , by section 49(1) of the Crown Minerals Amendment Act 2025 (2025 No 40).
- Section 89S(2): repealed, on , by section 49(2) of the Crown Minerals Amendment Act 2025 (2025 No 40).
- Section 89S(3): repealed, on , by section 49(2) of the Crown Minerals Amendment Act 2025 (2025 No 40).
- Section 89S(4): repealed, on , by section 49(2) of the Crown Minerals Amendment Act 2025 (2025 No 40).
- Section 89S(5): repealed, on , by section 49(2) of the Crown Minerals Amendment Act 2025 (2025 No 40).