Part 1BPermits, access to land, and other matters
Decommissioning of petroleum infrastructure and wells: Reporting requirements
89ZCDecommissioning cost estimate
A person who is, or will be, obliged, under this subpart, to carry out and meet the costs of decommissioning must submit a cost estimate of all anticipated decommissioning work (a decommissioning cost estimate) to the chief executive—
- at the prescribed times (if any); and
- within a specified time of the occurrence of prescribed events (if any); and
- on request from the Minister, within any reasonable time specified in the request.
The decommissioning cost estimate must—
- comply with the standards prescribed (if any) for developing that estimate; and
- meet any further prescribed requirements.
The Minister may require any person who submits a cost estimate under subsection (1) to supply further information relating to the cost estimate within a time specified by the Minister.
Notes
- Section 89ZC: inserted, on , by section 18 of the Crown Minerals (Decommissioning and Other Matters) Amendment Act 2021 (2021 No 53).