Regulated goods or services - Electricity lines services - Imposition of regulation under this Part

54I: Commission must make section 52P determination specifying how subpart applies

You could also call this:

"The Commission decides how rules apply to electricity line companies."

Illustration for Commerce Act 1986

The Commission has to make some decisions, called section 52P determinations, about how certain rules apply to companies that supply electricity lines services. You can read more about what these decisions are in the section 52P part of the law. The Commission must make these decisions as soon as possible after certain dates or events happen.

The Commission makes these decisions at different times, depending on the situation. For companies that were already subject to certain rules on 1 April 2009, the Commission follows the process set out in section 54J. If a company becomes subject to these rules because of a new order made under section 54H, the Commission makes the decision as soon as possible after the order starts.

The Commission's decisions are important because they help clarify how the rules apply to each company that supplies electricity lines services. You can find more information about these rules and how they are applied by reading the relevant parts of the law, such as section 52P and section 54H.

This text is automatically generated. It might be out of date or be missing some parts. Find out more about how we do this.

This page was last updated on

View the original legislation for this page at https://legislation.govt.nz/act/public/1986/0120/latest/link.aspx?id=DLM1940045.


Previous

54H: How exempt status can be lost and default/customised price-quality regulation can be applied to consumer-owned suppliers, or

"What happens when a consumer-owned electricity supplier no longer follows special rules"


Next

54J: Section 52P determinations setting out default price-quality paths applying from 1 April 2009, or

"Rules for electricity line prices and quality from 1 April 2009"

Part 4Regulated goods or services
Electricity lines services: Imposition of regulation under this Part

54ICommission must make section 52P determination specifying how subpart applies

  1. The section 52P determinations that specify how information disclosure regulation applies to each supplier of electricity lines services must be made as soon as practicable after 1 April 2009.

  2. The section 52P determinations that specify how default/customised price-quality regulation applies to each supplier of electricity lines services that is subject to that form of regulation as at 1 April 2009 are made as set out in section 54J.

  3. The section 52P determinations that specify how default/customised price-quality regulation applies to each supplier of electricity lines services that becomes subject to that form of regulation as a result of an Order in Council made under section 54H must be made as soon as practicable after the order comes into force.

Notes
  • Section 54I: inserted, on , by section 4 of the Commerce Amendment Act 2008 (2008 No 70).