Part 2AAcquisition or taking of land for critical infrastructure projects
Compulsory acquisition
39AAGMinister or local authority may proceed to take land if negotiations unsuccessful
This section applies if the Minister or a local authority, as the case may be, is unsuccessful in acquiring land required for a critical infrastructure project under section 39AAF because—
- no agreement has been reached with the owner; or
- section 18(7) applies.
The Minister or local authority may proceed to take the land.
For that purpose, sections 23 to 26 of Part 2 apply with the modifications set out in sections 39AAH to 39AAJ.
Notes
- Section 39AAG: inserted, on , by section 5 of the Public Works (Critical Infrastructure) Amendment Act 2025 (2025 No 46).