165ZP: Incomplete concurrent application
or “When an application for ocean use is sent back because it's not complete, there's a 20-day time limit to fix it or it's cancelled.”

You could also call this:

“Rules about when you need to ask for extra permissions before using the beach or sea”

If the regional council decides that more information is needed for your application, they must do this within 20 working days. This time starts after one of two things happens:

  1. If your application is complete, the council has 20 working days after the end of the 10-day period mentioned in section 88(3).

  2. If your application was not complete and you had to submit it again, the council has 20 working days from the day after you resubmit it under section 165ZP(3).

If the regional council decides that you need to get more consents, they will not do anything more with your plan change request. They will wait until you have applied for all the other consents needed and these applications are complete according to section 88(3).

This text is automatically generated. It might be out of date or be missing some parts. Find out more about how we do this.


Next up: 165ZR: Concurrent application to be declined or treated as withdrawn if plan change request declined or withdrawn

or “If a plan change request is rejected or withdrawn, the related application for aquaculture activity is also cancelled or withdrawn.”

Part 7A Occupation of common marine and coastal area
Plan change requests and concurrent applications for coastal permits in relation to aquaculture activities

165ZQAdditional consents

  1. If the regional council makes a determination under section 91(1), it must do so within 20 working days after—

  2. the expiry of the 10 working days specified in section 88(3), if the application is not returned as incomplete:
    1. the day after the application is lodged again under section 165ZP(3), if the application was returned as incomplete under section 88(3A).
      1. If the regional council determines that 1 or more further consents will be required, the regional council is not required to take any further action on the plan change request until the applications for the further consents have been lodged and accepted as complete under section 88(3).

      Notes
      • Section 165ZQ: inserted, on , by section 55 of the Resource Management Amendment Act (No 2) 2011 (2011 No 70).
      • Section 165ZQ(1)(a): amended, on , by section 109(1) of the Resource Management Amendment Act 2013 (2013 No 63).
      • Section 165ZQ(1)(b): amended, on , by section 109(2) of the Resource Management Amendment Act 2013 (2013 No 63).