Building Act 2004

Regulatory responsibilities and accreditation - Responsibilities of building consent authority that is not territorial authority or regional authority

237: Application of subpart

You could also call this:

"Rules for organisations that check building plans"

This subpart is for a stand-alone building consent authority. You need to know what a building consent authority is to understand this. It is an organisation that checks if building plans meet the rules.

This subpart applies to this type of organisation. The rules about this subpart were changed by the Building (Earthquake-prone Building Deadlines and Other Matters) Amendment Act 2024.

You can find more information about these changes in section 25 of the Act.

This text is automatically generated. It might be out of date or be missing some parts. Find out more about how we do this.

This page was last updated on

View the original legislation for this page at https://legislation.govt.nz/act/public/1986/0120/latest/link.aspx?id=DLM307890.


Previous

236: Effect of transfer, or

"When a job is given to a different local council, they can do it as if it was always their job, but they can also give it back."


Next

238: Duties of stand-alone building consent authority, or

"What a stand-alone building consent authority must do to follow the law"

Part 3Regulatory responsibilities and accreditation
Responsibilities of building consent authority that is not territorial authority or regional authority

237Application of subpart

  1. This subpart applies to a stand-alone building consent authority.

Notes
  • Section 237: replaced, on , by section 25 of the Building (Earthquake-prone Building Deadlines and Other Matters) Amendment Act 2024 (2024 No 49).