Building - Special provisions for earthquake-prone buildings - Remediation of earthquake-prone buildings

133AM: Deadline for completing seismic work on or before 1 April 2024

You could also call this:

"Finish earthquake safety work by 1 April 2024 or your building's special deadline"

If you own a building that is at risk of damage from earthquakes, you must do seismic work on it by a certain deadline. The deadline is different depending on where your building is and what type of building it is. In areas with low seismic risk, you have 35 years to complete the work.

If your building is in an area with medium seismic risk, you have 12 years and 6 months if it is a priority building, or 25 years if it is not. In areas with high seismic risk, you have 7 years and 6 months if it is a priority building, or 15 years if it is not. However, if your building is a heritage building, you might be able to get an extension on the deadline, as stated in section 133AO.

You can also check clause 2 of Schedule 1AA to see if it applies to your building, which might change your deadline. You must complete the seismic work on or before 1 April 2024 if that is your deadline. The deadline is measured from the date of the first EPB notice issued for your building.

This text is automatically generated. It might be out of date or be missing some parts. Find out more about how we do this.

This page was last updated on

View the original legislation for this page at https://legislation.govt.nz/act/public/1986/0120/latest/link.aspx?id=DLM7333546.


Previous

133AL: Territorial authority must issue EPB notice for earthquake-prone buildings, or

"Council must notify owners of earthquake-prone buildings and tell them how to make it safer"


Next

133AMA: Deadline for completing seismic work on or after 2 April 2024, or

"Finish seismic work on your building by the deadline, which is 2 April 2024 or later"

Part 2Building
Special provisions for earthquake-prone buildings: Remediation of earthquake-prone buildings

133AMDeadline for completing seismic work on or before 1 April 2024

  1. The owner of a building or part of a building that is subject to an EPB notice must complete seismic work on the building or part on or before the deadline specified in this section if that deadline is on or before 1 April 2024.

  2. The deadline is the expiry of whichever of the following periods, as measured from the date of the first EPB notice issued for the building or the part of the building (rather than any replacement EPB notice), is applicable:

  3. in an area of low seismic risk, 35 years for any building; and
    1. in an area of medium seismic risk, 12 years and 6 months for a priority building and 25 years for any other building; and
      1. in an area of high seismic risk, 7 years and 6 months for a priority building and 15 years for any other building.
        1. However,—

        2. if clause 2 of Schedule 1AA applies to the building or the part of the building, the deadline is the deadline determined in accordance with that clause; and
          1. if the building or the part of the building is a heritage building for which an extension is granted under section 133AO, the deadline is the expiry of the period of the extension, as measured from the deadline that would apply under paragraph (a) or subsection (2) if no extension were granted.
            1. Repealed
            Notes
            • Section 133AM: inserted, on , by section 24 of the Building (Earthquake-prone Buildings) Amendment Act 2016 (2016 No 22).
            • Section 133AM heading: replaced, on , by section 16(1) of the Building (Earthquake-prone Building Deadlines and Other Matters) Amendment Act 2024 (2024 No 49).
            • Section 133AM(1): replaced, on , by section 16(2) of the Building (Earthquake-prone Building Deadlines and Other Matters) Amendment Act 2024 (2024 No 49).
            • Section 133AM(4): repealed, on , by section 16(3) of the Building (Earthquake-prone Building Deadlines and Other Matters) Amendment Act 2024 (2024 No 49).