Building Act 2004

Building - Code compliance certificates, certificates of acceptance, and compliance schedules - Code compliance certificates

92: Application for code compliance certificate

You could also call this:

“This law explains how you ask for a certificate to show your building work follows the rules.”

When you finish building work that needs a building consent, you need to ask for a code compliance certificate. You should do this as soon as you can after the work is done. You need to fill out a special form to ask for this certificate.

You must send your request to the building consent authority that gave you the building consent. But if section 91(2) applies, you can send it to the building consent authority that will give you the code compliance certificate.

If any licensed building practitioners did work on your building, you need to include the records of their work with your request. These records are mentioned in section 88(1).

If you used a modular component in your building work, and the building consent authority used section 19(1)(da) when they gave you the building consent, you need to include a current certificate from the manufacturer for that component.

If your building work involved making or using a modular component, and you included a manufacturer’s certificate when you asked for the building consent (as mentioned in section 45(1)(bc)), you need to include a current certificate from the manufacturer for that component with your request for a code compliance certificate.

If your building work included any energy work that needed a building consent, you also need to include any energy work certificates that relate to that work.

This text is automatically generated. It might be out of date or be missing some parts. Find out more about how we do this.

View the original legislation for this page at https://legislation.govt.nz/act/public/1986/0120/latest/link.aspx?id=DLM306849.

Topics:
Housing and property > Home safety and repairs
Business > Industry rules

Previous

91: Building consent authority that grants building consent to issue code compliance certificate, or

“The authority that gave you permission to build is usually the one to say it's done properly, but sometimes another authority can do it if everyone agrees.”


Next

93: Time in which building consent authority must decide whether to issue code compliance certificate, or

“The building authority has to decide quickly if your building is safe and follows the rules.”

Part 2 Building
Code compliance certificates, certificates of acceptance, and compliance schedules: Code compliance certificates

92Application for code compliance certificate

  1. An owner must apply to a building consent authority for a code compliance certificate after all building work to be carried out under a building consent granted to that owner is completed.

  2. The application must be made—

  3. as soon as practicable after the building work is completed; and
    1. in the prescribed form; and
      1. either—
        1. to the building consent authority that granted the building consent for the building work; or
          1. if section 91(2) applies, to the building consent authority that it is proposed will issue the code compliance certificate.
          2. If applicable, the owner must include with the application any records of work provided by licensed building practitioners under section 88(1).

          3. If—

          4. the building work included the use of a modular component; and
            1. in granting the building consent, the building consent authority relied on section 19(1)(da),—
              1. the application under subsection (1) must be accompanied by a current manufacturer’s certificate for that component.

              2. If—

              3. the building work was the manufacture of, or included the use of, a modular component; and
                1. the application for building consent included a manufacturer’s certificate under section 45(1)(bc),—
                  1. the application under subsection (1) must be accompanied by a current manufacturer’s certificate for that component.

                  2. Repealed
                  3. If the building work comprises or includes energy work in respect of which a building consent has been granted, the owner must also include with the application any energy work certificate that relates to the energy work.

                  Compare
                    Notes
                    • Section 92(2A): replaced, on , by section 21(1) of the Building Amendment Act 2013 (2013 No 100).
                    • Section 92(3): inserted, on , by section 30 of the Building (Building Products and Methods, Modular Components, and Other Matters) Amendment Act 2021 (2021 No 21).
                    • Section 92(3A): inserted, on , by section 30 of the Building (Building Products and Methods, Modular Components, and Other Matters) Amendment Act 2021 (2021 No 21).
                    • Section 92(3): repealed, on , by section 21(2) of the Building Amendment Act 2013 (2013 No 100).